Alteryx Designer Desktop Discussions

Find answers, ask questions, and share expertise about Alteryx Designer Desktop and Intelligence Suite.
SOLVED

Calculate the no. of. days

Ronal_bal
8 - Asteroid

calculate the no. of. days when production status = 1 .

 

Below example, need to count date  between '2023-04-21' to '2023-05-15' as production status =1 . 

 

I need to calculate the same for different groups.

 

Ronal_bal_0-1682093320381.png

 

7 REPLIES 7
Luke_C
17 - Castor

Hi @Ronal_bal 

 

There are two different approaches as you mentioned two different sets of logic:

 

  1. 'calculate the no. of. days when production status = 1'
    1. Add a filter tool for Production Status = 1
    2. Use a summarize tool to Group By 'Group' and count the shift dates
  2. count date  between '2023-04-21' to '2023-05-15' as production status =1
    1. Probably requires a more robust set of logic in case there's 0s in the middle of the dataset, but could leverage multi-row tools, date time functions, etc. 

Attaching data (not a screenshot) and expected results would help determine the best approach. 

Ronal_bal
8 - Asteroid

Thanks for your reply, I'll try that. Attached the example as excel file

Ronal_bal
8 - Asteroid
Ronal_bal
8 - Asteroid

@Luke_C 

 

could you help me with multi-row formula?

binuacs
20 - Arcturus

@Ronal_bal One way of doing this

binuacs_0-1682104603083.png

 

RobertOdera
13 - Pulsar

Hi, @Ronal_bal 

 

Kindly consider the options below.

I hope you find them helpful - Cheers!

 

RobertOdera_0-1682113529113.png

 

RobertOdera
13 - Pulsar

You're most welcome @Ronal_bal!

Labels