Advent of Code is back! Unwrap daily challenges to sharpen your Alteryx skills and earn badges along the way! Learn more now.

Alteryx Designer Desktop Discussions

Find answers, ask questions, and share expertise about Alteryx Designer Desktop and Intelligence Suite.
SOLVED

Date starting change

Maanvendra
6 - Meteoroid

I have a column of dates

Date
30-04-2024
08-05-2024
09-05-2024
14-05-2024
17-05-2024
22-05-2024
24-05-2024


I want to get aditional column for which the starting day will be mon and with the duration of 2 weeks strating from 29-04-24 and with a gap of 2 weeks. so
the output will be as below.. this is a urgent requirement.

Date_Out
29-04-2024
29-04-2024
29-04-2024
13-05-2024
13-05-2024
13-05-2024
13-05-2024
2 REPLIES 2
Deano478
12 - Quasar

Hey @Maanvendra have a look at this Workflow attached

Maanvendra
6 - Meteoroid

Hi, this works .

Thanks a lot

Labels