How to checking on the Progression using Alteryx tools

shijieleong
7 - Meteor

Hi , 

 

Question: 

 

I want to track the progression of the sales target.

Current month is 10 month, and all the target are cumulative. I would like to find out with the current total sales number achieved at which month of the sales person meeting the target. 

 

Please refer to the attached data. 

3 REPLIES 3
MichelleL
Alteryx
Alteryx

@shijieleong Using a Join tool should get you the results you need.  Please see attached workflow and let me know if this works for you!

MichelleL_0-1654617804918.png

 

shijieleong
7 - Meteor

Hi Michelle, 

 

Thank you for your reply, my expected result is if the FC did not met current month target then what is the progression point, eg: 20002, 

FC did not meet month 10 target but the sales person has cleared month 5 target. 

 

Thanks 

MichelleL
Alteryx
Alteryx

@shijieleong I've added logic to choose which month the Sales meets the Target.  Let me know if this works for you :-)

 