Splitting the data between 2 dates

pachopra
7 - Meteor

I have below task in which there is a role and a  start date and end date and # of hours and I need to divide the hours/ business working days and find hrs per day

since in below case there are 131 business working days so 1040/131=7.93. Weekend dates can show 0 hours and thats fine

 

Reason is I need to understand by role and each month, how many hrs they are expected to work. The assumption is that they work same every day.

 

Thank you

 

INPUT:

 

KEY          Role                start date                end date                hrs

 

    1         Consultant        6/1/2020             11/30/2020              1040

 

OUTPUT:

 

key                      role                       date             month       year                hrs            

 

 1                         Consultant          6/1/2020            June       2020           7.93

 1                          Consultant         6/2/2020             June       2020           7.93

  1                         Consultant          6/3/2020            June        2020           7.93

 

  1                          and so on until...  11/30/2020        Nov        2020           7.93

 

hrs column will total at the end to 1040

 

2 REPLIES 2
CoG
14 - Magnetar

Generate Rows Tool is what you need to get the job done. Here is a sample workflow (just be aware that holidays are not considered at all; only weekends are omitted):

Screenshot.png

flying008
15 - Aurora

Hi, @pachopra 

 

FYI.

 

录制_2023_12_05_09_27_59_396.gif

Labels