Hi Team / @binuacs ,
could someone assist on the below?
Input:
Date |
01/01/2025 |
03/03/2025 |
Holiday list |
15/01/2025 |
10/03/2025 |
10/10/2025 |
OUtput:
excluded weekends and holidays after adding 15 days to date and take next possible weekday
Date | Output |
01/01/2025 | 17/01/2025 |
03/03/2025 | 19/01/2025 |
Solved! Go to Solution.
@Anjankumar2021 would you mind explaining the calculation of the output 17/01/2025
Date | No of days | after adding | Holiday list | Output |
01/01/2025 | 15 | 16/01/2025 | 15/01/2025 | 17/01/2025 |
after adding 15days the date should be 16/01/2025 but 15/01/2025 was holiday and no weekend came( Saturday and Sunday). excluded holiday and took next possible business day 17/01/2025
@Anjankumar2021 try the attached workflow