Hello Team,
From the below input:
Input | ||||||
Employee | Name | Start Date | End Date | Code | Duration | Dates |
1 | Ravi | 3/10/2025 | 3/11/2025 | Vacation | 16 | 3/10/2025 |
1 | Ravi | 3/10/2025 | 3/11/2025 | Vacation | 16 | 3/11/2025 |
2 | Shiv | 5/12/2025 | 5/14/2025 | Sick | 24 | 5/12/2025 |
2 | Shiv | 5/12/2025 | 5/14/2025 | Sick | 24 | 5/14/2025 |
2 | Shiv | 5/12/2025 | 5/14/2025 | Sick | 24 | 5/14/2025 |
3 | Raj | 6/11/2025 | 6/11/2025 | Floating | 8 | 6/11/2025 |
and trying to generate the following output:
Output | |||||||
Employee | Name | Start Date | End Date | Code | Duration | Dates | Actual Duration |
1 | Ravi | 3/10/2025 | 3/11/2025 | Vacation | 16 | 3/10/2025 | 8 |
1 | Ravi | 3/10/2025 | 3/11/2025 | Vacation | 16 | 3/11/2025 | 8 |
2 | Shiv | 5/12/2025 | 5/14/2025 | Sick | 24 | 5/12/2025 | 8 |
2 | Shiv | 5/12/2025 | 5/14/2025 | Sick | 24 | 5/14/2025 | 8 |
2 | Shiv | 5/12/2025 | 5/14/2025 | Sick | 24 | 5/14/2025 | 8 |
3 | Raj | 6/11/2025 | 6/11/2025 | Floating | 8 | 6/11/2025 | 8 |
Labels:
- Labels:
- Workflow
4 REPLIES 4
CoG
14 - Magnetar
‎02-05-2025
01:45 PM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Notify Moderator
There isn't a question here. What process are you using that you need assistance with? Just based off of what was provided, A Formula Tool with hard-coded value of 8 will get you from provided input to output.
‎02-05-2025
01:49 PM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Notify Moderator
Using Generate Row Tool i was able to split the Dates as per Start and End Date, however in the first table if a entry is for 3 day the duration show 24.. i need to split it again as 24/3 which should give me 8 hours per day if it for 2 day and the duration is 16.. it should give me 16/2 so 8 hours each date.
binuacs
21 - Polaris
‎02-05-2025
02:47 PM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Notify Moderator
@Hiteshp one way of doing this with the help of summarise tool and join tool
CoG
14 - Magnetar
‎02-05-2025
03:16 PM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Notify Moderator