Hello, I'm stuck on a problem and was hoping one of you could help me out. Thanks in advance for your help!

 

I'm trying to solve what date an order will be processed down to 0 orders based on the following conditions:

1. We process 2,500 orders everyday

2. Start from today's date (4/12/2021)

3. No unfulfilled orders before 4/1/2021

 

Here's a sample data set with the correct answer on the right. I'm trying to get to work dynamically and will need to scale this for many years into the future.

 

Order_DTOrdersProcessed_DT?Correct Answer:
4/1/20212000 4/12/2021
4/2/20214000 4/14/2021
4/3/20211000 4/14/2021
4/4/2021500 4/14/2021
4/5/20213000 4/16/2021
4/6/20212500 4/17/2021
5 REPLIES 5
Luke_C
17 - Castor
17 - Castor

Hi @macd279 

 

Do weekends/holidays need to be considered? 

macd279
7 - Meteor

No, everyday would be the same processing amount (2500) - Weekdays, weekends, holidays. 

apathetichell
20 - Arcturus

I would use running total and ceil division as attached...

macd279
7 - Meteor

Works great, thank you!

apathetichell
20 - Arcturus

Glad to hear it worked!