How do I translate the formula into an Alteryx formula

 

IF(AND(NOT($E2=""),$F2=""),ROUND($B2*0.44,0),"")

 

 

The below is my attempt:

 

IIF((![Scheduled Approval Drawings Due] and [Actual Approval Drawing Due]=""),([Total PE Hours]*0.44,"")

4 REPLIES 4
Luke_C
17 - Castor

Hi @ArianaMiller1 

 

Sample data is always helpful, but you could try something like this:

 

IIF([Scheduled Approval Drawings Due] !="" and [Actual Approval Drawing Due]="",[Total PE Hours]*0.44,null())

ArianaMiller1
5 - Atom

The formula did not have an error, but it did not return the same information:

 

Maybe I need to change the formula in Alteryx:

 

If Scheduled Approvals is Not Blank, but Actual Approvals are blank then I need it to show 44% of the Hours allowed for PEs, if approvals have been submitted then I need a blank space, and if this particular project dos not have approvals, then I need it blank.

 

Currently with the formula I have. Approvals are scheduled but not completed and should show 44% but shows null instead.

2014786 EI 28 60 ND 2023-03-06 [Null] 2023-03-27 [Null] 2023-04-03 [Null] 2023-04-10 [Null] 2023-04-17 [Null] 2023-11-14 2014786 70.3 70.3 35.15 [Null]

Luke_C
17 - Castor

Hi @ArianaMiller1 

 

I'd use the isempty function then, which checks for both empty ("") and null values. 

 

IIF(!isempty([Scheduled Approval Drawings Due]) and isempty([Actual Approval Drawing Due]),[Total PE Hours]*0.44,null())

 

Double check that your total PE hours field is a numeric value, otherwise it won't calculate correctly.

ArianaMiller1
5 - Atom

Luke, it worked! Thank you!