Calculate by Adding 2 Days from Date

KamenRider
10 - Fireball

Hi Guys,

 

Would someone help me how to get the date by 2 days but will not count weekends (Saturday and Sunday) as well as US holidays?

 

For example my date is September 1, 2023 (Friday)

Sept 2 and 3 are weekends so it will not be included in the count

Sept 4 is US Labor Day

 

So if I am going to add to days, the date should be September 6, 2023.

 

Please help me derive the formula.

 

Thanks and hope to hear from someone.

Kamen

12 REPLIES 12
rzdodson
12 - Quasar

@KamenRider are there any other countries holidays that need to be excluded? I am assuming Labor Day is the US' Labor Day.

Qiu
20 - Arcturus
20 - Arcturus

@KamenRider 
I went to this site and download the list of US holidays for 2023.

Then basically we will generate a fairly large range dattes from specified date then filter out weekends and Holidays.

Hope this will help.

0915-KamenRider.PNG

rzdodson
12 - Quasar

@KamenRider here is another approach.

Solution.png

 

The analytic app solution generates a list of holidays for a user-determined number of years (first section). Then, in the second section, I use the URLs created in the first section to bring in all holidays for that country over those years. Third, and finally, I test the date against whether we are on a weekend and there is a holiday. If those conditions are not met, I add two days to the Test Date.

 

Hope that helps you out! :) 

KamenRider
10 - Fireball

Hi @rzdodson 

 

Only US Holiday for now.

 

Thanks for asking.

 

Kamen

rzdodson
12 - Quasar

@KamenRider Not a problem. If you need additional countries, I have preloaded the app solution I posted above with the list of countries that should work for the app. Would require some minor configuration (another Drop-Down tool for country selection).

KamenRider
10 - Fireball

Hi @rzdodson 

 

Got an error. Can you help me debug? See below error.

 

kidkat.PNG

 

Thanks,

 

Kamen

 

 

rzdodson
12 - Quasar

@KamenRider it could be a number of different reasons. There is pretty detailed Alteryx Community that is posted here:

https://community.alteryx.com/t5/Alteryx-Designer-Desktop-Discussions/Error-transferring-data-Failur....

Alternatively, I can run the number of years for the US for the next number of years for you, switch the input to a yxdb for the holidays in that period, and then remove the JSON parse section. Dealer's choice.

 

KamenRider
10 - Fireball

Hi @rzdodson 

 

I suspected because of the external links. Our company does not allow external links. Is there any other way you could modify the workflow?

 

What is JSON parse section? I apologize, I am not much well verse in Alteryx, still learning.

 

Thanks,

Kamen

 

 

KamenRider
10 - Fireball

Hi @Qiu 

 

Your workflow seems to get the logic of my problem. May I know why did you use "add seven days' in the formula instead of 2 days as per my requirement?

 

Need to know so I can also explain it to my colleagues.

 

Thanks,

Kamen