Hi all,
I have two workflow and I need to put them in one yxmd.
This one run the first.
This one run next.
Is there any solution ?
You can copy the first one into the second one, or the second into the first one. Then put them into Control Containers and connect the two containers together. The 2nd work flow wont run until the first one is finished.
https://help.alteryx.com/current/en/designer/tools/developer/control-container-tool.html
Edit: I just noticed this was related to Server. I am not sure if control containers are available in the server. If they are, this would be the approach to take.
Hi I've tried. As you said, it just work on server, not on desktop.
Is there any other solutions?
@Nico67543How that ? It should work on Alteryx Designer (the Desktop). Do you have an error message ?