Scheduled a job to run once and job and ran overnight. This morning the "State" indicated "Complete"
Results tab. Results is a grey circle. Date completed is Monday January 1, 0001 12:00:00 AM (create date is correct).
Note other odd results. Files produced from job is about 1/10th completed.
This was one of 4 concurrent jobs running the other three started almost same time are still running.
I am trying to figure out what happened and why there is not error messages. Error logging is set to LOW. I am going to adjust to High and rerun after other jobs complete. The date Completed is somewhat baffling?
Any ide
@DataRangler it could be that the job did not run, or it could also be that it ran fine but for some reason the results could not be retrieved from the database (and its just a rendering issue). Please do open a case with Support when you get the logging turned up.