Hi

 

Is there a way in the alteryx scheduling to run the workflow in sequential order ? Example - I have two workflow A and B . i want to run workflow A First and when it is completed workflow B should start. Incase if workflow A fails than workflow B should not kickoff.

 

 

2 REPLIES 2
Chandler_Bing
8 - Asteroid

HI @jdevar243 

You can set the order of execution of the workflows from the designer itself.

Please refer this link ,the last option would be the easy one to begin with and then you can figure out the best option for your use case.

 

Hope this helps

 

Thanks

jdevar243
7 - Meteor

Thanks Tyrion .

 

I will check that and post the details .

 

Thanks