Sup y'all

 

I have a column of date information which is the date a list of issues were raised. These have a timeframe of six weeks (say 42 days) to be cleared.

 

I'm struggling to figure out how to add a column simply adding 42 days to the DateRaised. I guess using a formula but I am not the best at using the datetime functions? I'm looking for a column headed TargetDate which is DateRaisedNew + 42 days...

 

Capture.JPG

 

Please can anyone shed some light on this for me?

 

Cheers

Sidey

3 REPLIES 3
ivoller
12 - Quasar

How about

 

DateTimeAdd([DateRaisedNew],42,"days")

 

Iain

CharlieS
17 - Castor
17 - Castor

Hi, @Sidey1978.

 

You are correct that a Formula tool can take care of this for you. Enter a new Ouptut Field in the Formula tool with the following formula and that should be it.

 

DateTimeAdd([DateRaisedNow],42,"days")

 

 

Let me know if you have any other questions.

Sidey1978
8 - Asteroid

Thanks both for sorting that one for me!

 

I knew it was going to be a simple one....*facepalm*

 

Cheers!