Hello,

 

First time using Interface Date and I am having trouble updating a date feild connected to an action/interface and Select tool. In the picture below, I would like to change the "Date" column to a date that is manually input using interface. 

pmelikian_0-1599753841264.png

pmelikian_2-1599753965460.png

 

Thanks For Your Help,

 

Paul 

 

 

1 REPLY 1
Jonathan-Sherman
15 - Aurora
15 - Aurora

Hi @pmelikian,

 

The issue was your action tool, you're wanting to update the value so your action tool should be connected to the input tool and not the select.

 

Jonathan-Sherman_0-1599755776225.png

 

 

I've attached a revised version of the app for you! If this solves your issue please mark the answer as correct, if not let me know!

 

Regards,

Jonathan