Hi Team,

 

I have a date, basis on that need to calculate next 365 days.

The 1st 5days must be only working days and if 1st 5days falls under saturday, sunday then combine it to monday and assign consecutive day.

 

I am facing challenge while assigning a days

 

The situation i have replicated in excel file and attaching here for reference and PFA alteryx workflow.

 

Highlighted
Alteryx Certified Partner
Alteryx Certified Partner

Hi @GayatriPanigrahi ,

 

I'm attaching here a solution with a multi-row tool. I also changed a bit your generate rows conditions to bring data after the reporting date, it was generating previous dates.

 

Best,

Fernando Vizcaino