HELP: Parse Error: Invalid Type in operator >=

emartinez
6 - Meteoroid

Hi,

 

I cannot figure this out. I keep getting an error. The incoming [Date] field is a Date type so I don't understand why I'm getting an invalid type in operator message. I want the new field [Period] to be a string field. What am I doing wrong?

 

 

 

2 REPLIES 2
Rana_Kareem
9 - Comet

Hi @emartinez ..

 

The date after the operators should be in quotation marks. " "

alexnajm
18 - Pollux
18 - Pollux

Dates should still be in quotes!