Create date that is 25th of current month, but next business day if 25th is on a weekend

cmStuhl
7 - Meteor

Hi All, 

 

The output I am creating in my current workflow must have a date that is 25th of current month, but next business day if 25th is on a weekend. Currently the input date I have to work with will always be 5 days prior to the 25th (20th). Does anyone have a solution to figure out the correct date? 

 

 

Thanks,

Max

2 REPLIES 2
binuacs
21 - Polaris
cmStuhl
7 - Meteor

Had to change the Sunday to a 6 and Saturday to a 7, but this worked! thank you!