In case you missed the announcement: Alteryx One is here, and so is the Spring Release! Learn more about these new and exciting releases here!
Free Trial

Alteryx Designer Desktop Discussions

Find answers, ask questions, and share expertise about Alteryx Designer Desktop and Intelligence Suite.

Consumption Logic - to consume planned quantity from packing sheet

JArjoon
5 - Atom

Hello all, 

 

I am stuck on below issue. I have two files: 

 

- An order file: which shows per order & material, when are the expected delivery dates. The quantities here are the requested quantities. 

- A planning packing file: which shows per material & batch - when the batches will be released. The quantities here are the quantity in production. 

 

Order File

Capture1.JPG

 

Planned packing file: 

Capture2.JPG

My ask is to bring the Purchase Order number on the planned packing file. 

 

Expected results: 

I) I have three orders for material 1 (33k, 16k & 16k) - so for batch RER: POA; batch REZ: POA itself [as quantity from POA has not yet been consumed]; Batch REB: POB 

ii) Batch ZAC: POD

 

I have tried several options and am getting stuck.. Attached is the dummy data (in excel).

 

Any assistance is super appreciated. 

K

4 REPLIES 4
Kottapally_Ramesh
7 - Meteor

Hi @JArjoon 

I have used join & unique tool to get the Purchase Order number on the planned packing file.

 

Please check & let me know if the results are expected or not?

JArjoon
5 - Atom

Hello Ramesh, 

Thank you for replying. 

However, it did not provide the correct result. 

Capture3.JPG

PO A is 33,000 - it would be consumed by batch REB & RER. 

Batch REZ will need to go under PO B. 

Kottapally_Ramesh
7 - Meteor

Can you share your expected output, it will be easy to understand & implement the logic. 

JArjoon
5 - Atom

Capture4.JPG

 

Hello Ramesh, 

Pls see above. 

J

Labels